Gov’t to install 3,000 transformers to tackle power outages

logo

logo



The government says it will install about 3,000 transformers nationwide as part of a major intervention to fix distribution challenges linked to recent power outages, according to the Ministry of Energy and Green Transition.

Head of Communications at the Ministry, Richmond Rockson, disclosed this during an interview on Joy FM’s Super Morning Show, saying the programme forms a central pillar of ongoing efforts to stabilise electricity supply across the country.

“The government has provided the needed resources,” he said, adding that installation works have already begun in several parts of the country.

Mr Rockson explained that the initiative aims to address long-standing weaknesses in Ghana’s electricity distribution network, which has increasingly struggled to keep pace with rising demand in urban and fast-growing communities.

He said 30 new transformers are currently being installed in Tamale this week alone, while 11 power station transformers are being replaced in the Greater Accra Region. He also noted that more than 2,500 distribution transformers are being deployed across the country as part of the broader rollout.

According to him, the national grid operator, Netco, recently requested over 400 transformers, out of which 100 were supplied immediately, with the rest expected to follow shortly.

Mr Rockson said the challenges facing the distribution network are not new, but reflect years of underinvestment in that segment of the power value chain.

“The crisis has been decades in the making,” he said, noting that policy focus in previous years has largely been on generation and transmission rather than distribution infrastructure.

He cited a substation at Lasibi in Accra, which he said has been in operation for about 22 years without a major upgrade, despite significant population and commercial growth in the area.

The Ministry says the transformer rollout is being implemented in four phases — starting with a three-month emergency response phase, followed by a three-to-six-month phase, a six-to-twelve-month phase, and a longer-term 18-month infrastructure upgrade phase.

The full programme is expected to require at least GH₵4 billion in investment, as the government seeks to reduce outages and improve stability across the national grid.

DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.

DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.


Source: www.myjoyonline.com